The identification and structuring of some components of a project is not clear enough to convert the starting or interim project schedule into an optimised master schedule.
Impact
Unusable project schedule.
Recommendation
Describe the scope as an explicit hierarchical product breakdown structure, defining the planning work packages, work packages and their decomposition into project activities. Define the resources needed for each activity.