Resource leveling and scheduling

Success Problem

What is the difference between resource leveling and resource scheduling

Impact

In the resource leveling it is impossible to postpone the project end date contrary to the resource scheduling.

Recommendation

Resource leveling is the determination of start dates and of end dates, or of activity durations so that the project resource histograms are continuous. Resource scheduling is determination of the start dates and end dates, res-pectively activity durations so, that the resource histogram for individual types of resources nowhere exceed the resource awailabilty. In contrast to the resource leveling it is possible to postpone the project end date in order to respect the resource availabilty. The activities can be postponed (or prolonged) also over the total float of the activity.

Category

0 Comments

Forgot Password?

Don’t have account? Register here!

Please read the Terms of Use and Privacy Notice

User Agreement:
Check here to indicate that you have

We have sent an email with a confirmation link to your email address. In order to complete the registration, please click the confirmation link.

The link expires within the next 14 days.

Please check, whether the email is in the junk folder, since confirmation mails with backlinks are sometimes classified as spam.

Please press the button.
Save All Changes.